| Reference |
17/00861/ER |
| Subject |
Land At
Britannia Place
Ayr
South Ayrshire
|
| Proposal |
Erection of 22 dwellinghouses - Stage 1 - Foundations, substructure, floor slab and underground drainage |
| Value of work |
£2300000 |
| Area team - Officer |
SOUTH -
Mr Andrew Richmond
|
| Application status |
BCO - Building Work Complete
|
| Received |
06 October 2017 |
| Date 1st response |
20 November 2017 |
| Warrant issued |
28 February 2018 |
| Completion Decision Date |
19 February 2019 |
| Completion Type |
BCO - Building Work Complete
|
| Applicant |
CCG (Scotland) Ltd |
| |
1 Cambuslang Road
Glasgow
G32 8NB |
| Agent |
Robert Potter & Partners LLP |
| |
R Jonathan Potter
169 Elderslie Street
Glasgow
G3 7JR |
| EPC Date |
24 January 2019 |
| Energy Efficiency Rating (A- G) |
B |
| Environmental Impact (CO2) Rating |
11 |
| Continuing Requirements |
All electrical work
|